- Task: Lowest unit of work. Smallest traceable item on project work plan and forms basis of work breakdown structure. Results in a new or revised work product.
 
- Work Product: Output of a task. Required to meet project objectives. Need not be a document. May or may not be a deliverable.
 
- Dependency: Define relationships between tasks or activities. 
 
- Process: Usually a sub project and can span more than one phase
 
- Phase: Temporary grouping of tasks. Natural point for milestones and checkpoints.
 
- Lifecycle Milestone: Occurs at phase boundaries. Assure objectives of phase are met. Assure readiness of project to move to next phase. 
 
- Activity: Next Level below a phase. Groups related tasks. Results in milestone or deliverable. May be from different processes. Begin and end in the same phase.
 
There are 4 types of dependencies:
- Predecessors
 
- Successors
 
- Overlap
 
- Gap
 
There are 5 Lifecycle Milestones defined in OUM. Their acronym are 
LO, LA, IOC, SP and SO.
- LO = Lifecycle Objective
 
- LA = Lifecycle Architecture
 
- IOC = Initial Operating Capability
 
- SP = System Production
 
- SO = Sign-off 
 
 